Consruction work at Over roundabout

The County Council's web page about this is here.

Work started on 30 April and will last for 18 weeks, finishing in August 2018.

There will be no lane closures between 7am – 9:30am and 3:30pm – 6pm throughout the scheme.

All daytime works will be completed using lane closures with the roundabout remaining open. Delays are expected but access will still be possible.

Although some weekend working may be necessary, the majority of the work will take place on weekdays. At present there are only two weekends identified (4 - 5 and 11 - 12 of August) where work will be carried out to resurface the roundabout  - see details below. Further information on road closures will be provided at the time.

Road Closures:

A40 Westbound (between Longford Roundabout and Over Roundabout) will be closed overnight from 29 May to 15 June between 7pm – 6am. The diversion can be viewed here (PDF, 6 MB) .

A417 Southbound (approach to Over from Maisemore) will be closed overnight from 29 May to 13 June between 7pm – 6am. The diversion can be viewed here (PDF, 5.2 MB) .

Resurfacing of the roundabout will take place over two weekends in August (4 – 5 and 11 – 12 August). Road closures will be in place from 7pm Friday evening through to 6am Monday morning. Please note that further restrictions will be in place during the resurfacing of the roundabout but access will be maintained where possible.

More details and traffic advice will be issued nearer the time.

Construction Update Bulletins

If you would like to be added to the distribution list for these bulletins please contact  christian.chambers@britanniaconstruction.co.uk
 
Bulletin 1 - 17 May 2018 (PDF, 270.5 KB)